Ardnagappary 110 kV 2018-2019
Project Description:
The new ESB Networks Ardnagappary 110/38kV Substation is
located outside Bunbeg, Co. Donegal.
Omexom scope was the Electrical installation of:
During Phase 1 (Civils works) Omexom was also responsible for the Electrical fit-out of the substation building ahead of electrical installation.

Booltiagh 110kV Substation -Seahound Wind Developments 2017-2019
Project Description:
Substations: AIS - Air insulated substation
Expertise: Underground cables: Trenching, excavation and back filling Civil foundations : Foundations design (surface and deep)
Voltage (kV) : 110
Start date : 09/2017 - End date : 07/2019

Castlecraig Wind Farm - 2018
Project Description:
Castlecraig wind farm is a 25MW wind farm based in Tyrone, Northern Ireland, which comprises of 10 Nordex Turbines.
The Omexom Ireland & Renewables Business Unit undertook full project scope for the electrical balance of plant; including design, installation, commissioning, andsupervision of works.
Omexom provided a range of experienced support personnel including project management, plantelectricians, commissioners, and senior authorised personnel.
Technologies Used:
Customer Benefits:

Bann Road PV Farm 33kV Substation 2016-2017
Project Description:
Introduction
Bann Road PV Farm is a 45.75 MWp Solar Farm located in Co. Antrim, Northern Ireland.
Omexom UK Renewables were responsible Installation of:

Tullabrack 110kV Substation 2016-17
Project Description:
Facilitating works included the 110kV Cable Installation from the existing Ennis / Booltiagh-Moneypoint Line Cubicle, new 38kV
Trafo Cubicle, new 38kV Feeder Cubicle, 10MVA 38kV/MV
Transformer.
In addition, an extension to existing control and battery rooms
was required.

Cherrywood 110kV GIS Substation 2015-2017
Project Description: