Ryebrook 110kV GIS Substation 2014-2015
Project Description :
The Ryebrook 110kV GIS Substation is located to the rear and to the NW at Intel Plant, Leixlip, Co. Kildare. The Substation major works element is outlined as follows:
Five 110kV Cable Bays
Two 110kV Wing Coupler Bays
A double 110kV Busbar
Eleven Transformer Bays
Six 110kV Sectionaliser Bays
Substation Control Building, including Control / Protection
Room, Battery Room and WC
An SCS Micro SCADA based Substation Control System