The 132kV Double Circuit K-Line route is located in Cornwall, and required the replacement of 8 PL16 towers and the re-tensioning of 35 sections of single 175mm2 ACSR LYNX conductor.
All the existing conductor fittings and insulators were replaced with equivalent polymeric sets.