The latest news from the network

News

  • Business Unit News / Ireland

    Lenalea Update

    On the 3rd of August, Omexom Ireland successfully energised Lenalea 110kV/33kV substation in Co. Donegal, Ireland. The Lenalea windfarm project included a 4 bay 110kV AIS substation, 2 110kV OHL connection circuits, 110/33kV Transformer, 33kV switchgear and reactive power compensation.

    Read more
  • Ireland / Renewables / Substations / Substations

    Omexom Ireland near completion of the Gorman 110/20kV Substation

    Omexom Ireland are finishing up work on the new Gorman 110/20kV substation. The substation is located 2km outside of Slane in county Meath, Ireland, with work starting in July 2021 and finalising by the end of January 2022. The €2.4M contract was awarded from Scottish Power Renewables for the complete design & build of the 110/20kV substation to enable the connection of a 50MW battery storage complex.

    Read more